Small error halts big ramp on Spokane Street Viaduct

A mistake of five inches forced a private contractor to tear down a ramp it was building on Seattle's Spokane Street Viaduct, just as progress was becoming visible to aggravated motorists who have endured serpentine detours, earthshaking noise and traffic delays for more than a year.

Seattle Times staff reporter

A mistake of about five inches forced a private contractor to tear down a ramp it was building on Seattle's South Spokane Street Viaduct, just as progress was becoming visible to aggravated motorists who have endured serpentine detours, earthshaking noise and traffic delays for more than a year.

The ramp on First Avenue South was rising from the roadbed toward the viaduct when a worker noticed last week that the freshly poured concrete footing wasn't lining up the way it was supposed to.

After considering its options, PCL Construction of Bellevue opted to tear down 160 feet of concrete and start over.

"It's our mistake, and we own those things," said Anthony Sturgess, PCL operations manager, who estimated the error will cost the company between $20,000 and $25,000. A surveying error created the misalignment, but the company hadn't identified how the error occurred, Sturgess said.

The tangle of rebar and concrete was expected to be trucked away Friday.

The First Avenue South ramp is part of a series of improvements designed to improve traffic flows on and around the Spokane Street Viaduct. When completed, the 300-foot, two-way ramp will funnel cars to and from the viaduct's westbound lanes.

Despite the mistake, PCL still expects to finish the ramp by fall, he said.

That's good news for motorists and nearby businesses.

"It pains me just to have to watch this all happening again," said Mark Hergert, a railroad-track modeler/programmer who has a front-row view of the action from his workplace at Nortrak. "It was so nice to see progress being made."

The Seattle Department of Transportation is overseeing the project. Spokeswoman Mary Beth Turner said the mistake resulted in a five-inch discrepancy. "They built it straight when it was supposed to be curved. People aren't always perfect. Mistakes happen."

Susan Kelleher: 206-464-2508 or skelleher@seattletimes.com

Due to incorrect information from the Seattle Department of Transportation, this story incorrectly stated that PCL Construction was also responsible for building a second ramp on Fourth Avenue South. PCL was not involved with the Fourth Avenue South ramp, which came in under budget and ahead of schedule. That ramp was constructed by MidMountain Contractors of Kirkland.

E-mail E-mail article      Print Print      Share Share

More Local News

UPDATE - 09:46 AM
Exxon Mobil wins ruling in Alaska oil spill case

NEW - 7:51 AM
Longview man says he was tortured with hot knife

Longview man says he was tortured with hot knife

Longview mill spills bleach into Columbia River

NEW - 8:00 AM
More extensive TSA searches in Sea-Tac Airport rattle some travelers

More Local News headlines...

News where, when and how you want it

Email Icon

Comments
No comments have been posted to this article.

advertising

Video

Advertising

Marketplace

Pebble Beach brings together rare Ruxtons new
With its pioneering front-wheel drive, low-slung silhouette and cat's-eye headlamps, the multicolored Ruxton automobile seemed destined for greatness ...
Post a comment

Advertising