New viaduct speediest option, studies show

If the Alaskan Way Viaduct were replaced by another elevated highway, a driver making his way from Seattle's Greenwood neighborhood to Seattle-Tacoma International Airport would arrive 10 minutes sooner than if the replacement were a surface boulevard, according to findings released Thursday by the Washington Department of Transportation.

Seattle Times staff reporter

8 viaduct replacement options

A) A four-lane boulevard along Alaskan Way, complete with multiple stoplights and improvements to Interstate 5.

B) A four-lane boulevard along Alaskan Way, but with more transit and improvements to downtown surface streets. This option would create about 80 feet of open space along the waterfront.

C) A six-lane Alaskan Way-Western Avenue couplet. The two northbound lanes would be on Western and the southbound lanes on Alaskan Way. This plan would create 110 feet of open space on the waterfront.

D) A four-lane elevated viaduct, with the lanes side by side, not stacked. This would be similar to the existing viaduct and would retain the views.

E) The most unusual proposal comes from Frank Chopp, speaker of the state House of Representatives: a four-lane elevated viaduct that would be covered by a park, with buildings underneath. The replacement would be about as high as the existing viaduct. Chopp envisions selling development rights below the viaduct to help defray the cost of the structure. In the travel-time analysis, released by the state on Thursday, this option had among the fastest commutes.

F) A four-lane bored bypass tunnel that would start near Qwest Field and go under Western Avenue and Post Alley. The only offramp would be at King Street. This tunnel would be 100 feet deep in places and would go under the Burlington-Northern railroad tracks. It would also go under the Battery Street Tunnel.

G) A cut-and-cover tunnel along the central waterfront. It would be four lanes and merge onto an elevated roadway at Stewart Street and a surface street by the Pike Place Market.

H) A four-lane lidded trench, with two lanes in each direction. There would be openings in the cover to ventilate the roadway. This plan also calls for signals on streets north of the Battery Street tunnel.

It's a 10-minute advantage.

If the Alaskan Way Viaduct were replaced by another elevated highway, a driver making his way from Seattle's Greenwood neighborhood to Seattle-Tacoma International Airport would arrive 10 minutes sooner than if the replacement were a surface boulevard, according to findings released Thursday by the Washington Department of Transportation.

Research shows such a trip during the afternoon commute would take 47 minutes on a surface boulevard and 37 on an elevated viaduct.

Travel time is just one part of a complicated mosaic of 27 measures that will be used to make a final decision among eight viaduct-replacement options under consideration. On Thursday the state released its analyses of trip times — on elevated roadways, on surface boulevards and in tunnels.

The state plans to narrow the eight replacement options to three in December and to make the final selection before the end of the year.

Many of the city's industrial leaders have been pushing for another elevated viaduct, and the Department of Transportation (DOT) travel-time study did find it would save time for freight. From First Avenue South to Interbay on the viaduct during the morning commute would take 16 minutes on an elevated viaduct, compared with as much as 26 minutes on a surface street. From Ballard to Sodo, during the morning southbound commute, it would take 27 minutes on surface streets, as long as 23 minutes in a tunnel, or just 14 minutes on an elevated viaduct.

The travel-time equation, said Ron Paananen, viaduct project manager, will cause some people to weigh the value they put on their time.

While the elevated options appear to move vehicles faster, the tunnel options could be just as fast if the state can figure out a way to smooth tunnel entries and exits, Paananen said. "The elevated may be the fastest trip, but at what cost?" he asked.

In June, the DOT released eight finalist plans for replacing the viaduct. They include three ideas for surface boulevards, two for aerial viaducts, and three tunnel options.

High costs could eliminate some of the plans. While the state at one time had $2.8 billion available to rebuild the viaduct, it has already spent a large amount of that money to replace the south part of the existing viaduct, and DOT officials said only about $1.5 billion remains.

The DOT plans to release cost estimates for each of the eight viaduct options next week; it's not known whether any could be built with the existing funds. Paananen said the state is now looking at other possible funding sources. The DOT may have to go back to the state Legislature for more money.

Susan Gilmore: 206-464-2054 or sgilmore@seattletimes.com

Copyright © 2008 The Seattle Times Company

More Local News headlines...

Print      Share:    Digg     Newsvine

Comments
No comments have been posted to this article.

advertising

UPDATE - 09:46 AM
Exxon Mobil wins ruling in Alaska oil spill case

NEW - 7:51 AM
Longview man says he was tortured with hot knife

Longview man says he was tortured with hot knife

Longview mill spills bleach into Columbia River

NEW - 8:00 AM
More extensive TSA searches in Sea-Tac Airport rattle some travelers

Advertising

Video

Marketplace

Advertising